Phase Wise Highlights

Phase 1
• This Phase was for Go-Live of Vijaya Bank Branch
​​
• Performed Functional Testing and Data Migration testing for 6 Mock Runs for Pilot Branch of Vijaya Bank
​​
• Data Migration Testing was performed using Excel Macro with Manual Intervention.

Phase 2
• This Phase was for Go-Live of 9 Vijaya Bank Branches
​
• Performed Functional Testing and Data Migration testing for 2 Mock Runs Before Go-Live & After Go-Live
​
• Data Migration Testing was performed using Excel Macro (Java Based Code) with Limited Manual Intervention

Phase 3
• This Phase was for Go-Live of 10 Vijaya Bank Branches.
​
• Team reduction from 15 resources to 9 Resources
• Data Migration Testing was performed using MS-SQL Database Approach

Phase 4
• This Phase was for Go-Live of 10 Vijaya Bank Branches.
​
• Team reduction from 15 resources to 9 Resources
​
• Data Migration Testing was performed using MS-SQL Database Approach

Phase 5
• This Phase was for Go-Live of 135 Vijaya Bank Branches
​
• Data Migration Testing was performed using MS-SQL Database Approach

Phase 6
•This Phase was for Go-Live of 3 Dena Bank Branches
​
•Data Migration Testing was performed using MS-SQL Database Approach

Phase 7
•This Phase was for Go-Live of 369 Vijaya Bank Branches
​
•Data Migration Testing was performed using MS-SQL Database Approach
​
•Performed Testing on UAT Server and Pre-Prod Server
​
•Also Performed Post Go-Live Testing

Phase 8
•This Phase was for Go-Live of 467 Vijaya Bank Branches
​
•Data Migration Testing was performed using MS-SQL Database Approach
​
•Performed Testing on UAT Server and Pre-Prod Server
•Also Performed Post Go-Live Testing

Phase 9
•This Phase was for Go-Live of 912 Vijaya Bank Branches
​
•With this Migration, All Vijaya Bank Branches would get Merged into BOB
​
•Performed Testing on UAT Server and Pre-Prod Server
​
•Also Performed Post Go-Live Testing

Phase 10
•This Phase was for Go-Live of 365 Dena Bank Branches
​
•Dena Bank Migration started with this phase
​
•Performed Testing on UAT Server and Pre-Prod Server
​
•Also Performed Post Go-Live Testing